The Asbestos Group were instructed to remove the fire damaged asbestos slate roof from a three storey student accommodation building . Access was difficult to the rear and the front had dormer windows with asbestos tile cladding.
Our operatives have the appropriate accreditation for using mobile platforms and the job was completed on time which included stripping out contaminated contents to the first and ground floor.
Asbestos Image Gallery
AIB window panelling
Asbestos cement external building panel
Asbestos cement drainage pipe
Asbestos panelling around gas meter (damaged exterior)
Asbestos cement roof (damaged exterior)
Asbestos soffit
Asbestos textured coating
Damaged asbestos lagging on hot water pipes
Damaged Asbestos Panelling
Pieces of AIB
Damaged asbestos pipe lagging and debris
Sprayed limpet asbestos on the underside of an asbestos cement roof
Pipe insulated using both asbestos lagging and rope
Torn asbestos pipe lagging
Unscrewing of an AIB ceiling tile.jpg
Wall with trowelled loose asbestos
AIB ceiling tiles in a corridor
asbestos containing floor tiles in a corridor
Pieces of AIB
Most Recent News
- Asbestos Group Appoint General Manager 20 November 2024
- Asbestos Commercial Roof Removal along with Contaminated Contents. 13 June 2024
- Asbestos Removal and Demolition 4 December 2023
- The Asbestos Group 17 Years Trading 18 July 2023
- Principal Contractor JCT Minor Works Building Contract 24 May 2023
- Major Loss Claim in Essex. 9 January 2023
- Wennington fire:Contaminated Building Deconstruction & Contents Removal. 8 September 2022
- Demolition Contractor Stored Dangerous Asbestos 7 April 2022